Current Projects

    St. Pius X Catholic Parish

    Erhardt replaced and re-piped the church’s boiler room, replacing and installing high-efficiency boilers.
     
    Most recently, Erhardt broke ground on what is the final phase of the project in October 2018. This final phase of construction includes a new 2,736-square-foot addition that will accommodate a multi-purpose room and cafĂ© to host youth activities, as well as general assembly. 

    There will be a 2,500-square-foot renovation on the interior of the building. This will include expanding the vestibule into a larger gathering space to create a more hospitable and welcoming environment.  
     
    The project will be completed following the milling and repaving of parking lots in the summer of 2019.   

    Project at a glance

    • Location: Grandville, Michigan
    • Architect/Engineer: Progressive AE
    • Footage: 5,236 SF

    Services